We pride ourselves on our thorough pre-construction process - ensuring the journey to construction is as seamless as possible.
Just Starting?
FIRST STEPS
DISCOVERY
MEETING
Meeting Agenda
OVERVIEW
A general review of the building site and potential considerations specific to your block and ideas.
CONSULTANTS
Basic estimate of pre construction fees from external consultants - Designer, Engineer, Town Planner ect.
FEASIBILITY
Feasibility of client desired outcome based on block, budget and size and style of house.
RATES
Basic m2 rate of build based on verbal client information about ideal build.
RECS
Recommendation of architect/designers based on client brief and budget.
EDUCATION
Education on typical timeline to get from here to a build contract.
WALKTHROUGH
Book time for client to see and walk through a current Tide build to show level of finish.
MOVING FORWARD
PHASE ONE
Information Gathering & Preliminary Costing - $2450 inc. GST
01.
First discovery design meeting with Client and Designer to obtain brief and inspiration for facade and layout.
02.
Detailed proposal of build costs after concept plans are complete. Allowances/estimates to be used for selections and information not yet obtained (based off clients brief/budget).
03.
Meeting with Client to review proposal and Tide value management worksheet. (VM worksheet is a detailed review of efficiencies and build costs to optimise plans).
04.
Refine proposal and plans based off first proposal cost vs budget.
DRAFTING AND FINALISING
PHASE TWO
Engage Tide on Preliminary Agreement / Deposit of 0.75%
05.
Engage consultants, arrange Engineer, Town Planner, Interior Designer. (Interior designer / town planner not always required).
06.
Review consultants plans and value manage for efficiencies. Work with client to optimise.
07.
Tide begins tender process and builds out scope of works for each trade and complete detailed take offs for all materials to provide a fixed quote.
08.
Review proposal with Client and make adjustments if required to value manage or meet budget. Repeat above steps if budget is not met. Review all remaining documentation to assist client to Certification.
09.
Draft fixed price build contract and full gant chart build schedule.
tide constructions timeline
Timeline of Events Prior to Plans
Week 1
Engage Tide
Engage Tide Constructions Phase One
Engage Building Designer
Week 2
Design & Survey
Client Meeting with Designer & Builder to
discuss design brief & inspo
Engage Surveryor for contours & boundaries
Week 4-5
Concepts & Estimates
Designer release 1st concept plans
Builder release 1st estimate
Client Meeting to discuss plans & budget
Refine plans & re estimate as required
Builder release 1st estimate
Client Meeting to discuss plans & budget
Refine plans & re estimate as required
Week 6
Agreements & Selections
Engage Engineer
Engage Interior Designer/begin selections
Engage Tide Constructions Prelim Agreement
Engage Interior Designer/begin selections
Engage Tide Constructions Prelim Agreement
Week 7
Designer & Supplier
Client Meeting with Interior Designer
Visit suppliers to make selections
Visit suppliers to make selections
Week 9-10
Finalise & Propose
Client Meeting with Interior Designer to finalise
selections
Engineer release plans
Tide Constructions begin fixed price proposal & specs
Engineer release plans
Tide Constructions begin fixed price proposal & specs
Week 11-12
Review & Refine
Client Meeting to review final fixed price build
proposal
Refine above steps as required
Refine above steps as required
Week 11-12
Signing
Tide Constructions to prepare final Contract for signing.
Already Have Plans?
FIRST STEPS
DISCOVERY
MEETING
Meeting Agenda
OVERVIEW
A general review of the building site and plans
CONSULTANTS
A general review of external consultants already engaged by client.
FEASIBILITY
Feasibility of client desired outcome based on block, budget and plans.
RATES
Basic m2 rate of build based on verbal client information about ideal build.
RECS
Review of architect/designer based on client choice.
EDUCATION
Education on typical timeline to get from here to a build contract.
WALKTHROUGH
Book time for client to see and walk through a current Tide build to show level of finish.
MOVING FORWARD
PHASE ONE
Information Gathering & Preliminary Costing - $2450 inc. GST
01.
Detailed proposal of build costs after concept plans are complete. Allowances/estimates to be used for selections and information not yet obtained (based off clients brief/budget).
02.
Meeting with Client to review proposal and Tide value management worksheet. (VM worksheet is a detailed review of efficiencies and build costs to optimise plans).
03.
Refine proposal and plans based off first proposal cost vs budget.
DRAFTING AND FINALISING
PHASE TWO
Engage Tide on Preliminary Agreement / Deposit of 0.75%
04.
Engage consultants, arrange Engineer, Town Planner, Interior Designer. (Interior designer / town planner not always required).
05.
Review consultants plans and value manage for efficiencies. Work with client to optimise.
06.
Tide begins tender process and builds out scope of works for each trade and complete detailed take offs for all materials to provide a fixed quote.
07.
Review proposal with Client and make adjustments if required to value manage or meet budget. Repeat above steps if budget is not met. Review all remaining documentation to assist client to Certification.
08.
Draft fixed price build contract and full gant chart build schedule.
tide constructions timeline
Timeline of Events With Client Provided Plans
Week 1
Engage Tide
Engage Tide Constructions Phase One
Week 2-3
Estimate & Discuss
Builder release 1st estimate
Client Meeting to discuss plans & budget
Refine plans & re estimate as required
Client Meeting to discuss plans & budget
Refine plans & re estimate as required
Week 4
Select & Agree
Engage Engineer (if required)
Engage Interior Designer/begin selections
Engage Tide Constructions Prelim Agreement
Engage Interior Designer/begin selections
Engage Tide Constructions Prelim Agreement
Week 5
Meet & Supply
Client Meeting with Interior Designer
Visit suppliers to make selections
Visit suppliers to make selections
Week 6-7
Finalise & Propose
Client Meeting with Interior Designer to finalise selections
Engineer release plans
Tide Constructions begin fixed price proposal & specs
Engineer release plans
Tide Constructions begin fixed price proposal & specs
Week 8-9
Review & Refine
Client Meeting to review final fixed price build
proposal
Refine above steps as required
Refine above steps as required
Week 10-11
Signing
Tide Constructions to prepare final Contract for signing.